In Kandy my first job under Mr.V.Chinniah,the site engineer was this.I took over from another ES and manage to complete the work within 2 weeks.It was a surprise to my boss as the scheduled day of completion was 4 weeks from take over.
The pole mounted substation installed on two very heavy RC poles,manufactured by State Engineering Corporation of Sri Lanka.Each pole is 1.3 metric tons of weight.The erection location was in a estate terrain by the side of estate road. We did not have cranes those days to handle heavy work.